APM PMQ risk management: what you need to know
A risk is an uncertain event that has not happened yet. An issue is one that has. The APM PMQ tests whether you can identify, assess, respond to and monitor risks, including opportunities, not just describe a risk register.
Updated
Risk is where the gap between knowing the vocabulary and being able to use it shows up most clearly. Everyone can define a risk register. Very few candidates can write five marks' worth of convincing argument about what to do in a specific situation, which is what the paper asks.
Risk or issue
The distinction is simple and it's examined constantly, so have it precise.
A risk is uncertain. It might happen. It has a probability and an impact, and because it hasn't happened yet you can still do something about it in advance.
An issue has happened, or is happening now. Uncertainty is gone. You are no longer managing probability, you're managing consequences.
The reason this matters beyond terminology: they need different handling and different routes. Risks are managed proactively by the project, within an agreed appetite. Issues frequently need escalating, because they often exceed the project manager's authority to resolve.
A risk that materialises becomes an issue. That transition is a favourite exam scenario, and the good answer is rarely "put it in the issue log."
Opportunities are risks too
This trips people up. Risk in this syllabus is uncertainty in both directions. An uncertain event with a positive impact is still a risk, and it should be managed rather than hoped for.
That gives you two families of response, and being able to name both cleanly is worth marks:
For threats: avoid it, reduce it, transfer it, or accept it.
For opportunities: exploit it, enhance it, share it, or reject it.
If a question mentions a possible upside, a supplier who might deliver early, a technology that might cut effort, and your answer only discusses mitigation, you've answered half of it.
Risk owner and action owner
Another distinction that reliably appears.
The risk owner is accountable for the risk overall: monitoring it, judging whether the response is working, escalating when it isn't.
The action owner is responsible for carrying out a specific response action.
They're often different people, and they should be. The risk owner is usually whoever is best placed to see the risk coming and has the authority to act; the action owner is whoever actually does the task.
What a good scenario answer looks like
Take a realistic case. A project depends on a specialist component with a single credible supplier, and their lead time consumes most of the float before an immovable installation window.
A weak answer says: log it as a high risk with a mitigation plan.
A stronger answer works the process. Identify it as a schedule risk with a single point of failure and a hard downstream dependency. Assess it: high impact because the installation window cannot move, moderate probability, and critically, high proximity, meaning it will bite soon rather than eventually. Then respond deliberately, and say which response you've chosen and why: reduce it by placing the order early and paying to hold a slot, or transfer part of the exposure contractually, or accept it with a fallback already agreed, such as a temporary alternative that keeps the window intact. Then monitor: named owner, reviewed on a defined cadence, with a trigger point at which the fallback is invoked rather than debated.
Notice that the register is barely mentioned. The register is where the thinking gets recorded. The marks are in the thinking.
Proximity is worth carrying into the exam, incidentally. Two risks with identical probability and impact are not equally urgent if one lands next month and the other in a year.
Qualitative and quantitative
Know the difference and when each fits.
Qualitative assessment ranks risks by judged probability and impact so you can prioritise. It's quick, it's subjective, and it's what most projects run on day to day.
Quantitative assessment models the numerical effect on cost or schedule. It costs more effort and needs decent data, so it tends to be reserved for large or high-exposure projects, or specific decisions worth modelling.
Qualitative first, quantitative where the stakes justify it.
The point to hold onto
However thorough your register, it prevents nothing on its own. Risk management works when a response was agreed in advance and someone acted on it, which is exactly why exam questions describe situations rather than asking for definitions.
Essentially: know the risk and issue split, remember opportunities count, keep risk owner and action owner separate, and when a scenario appears, walk the process and say what you'd do and why.

Founder,Learn in Curve![]()
Frequently asked questions
Identifying, assessing, responding to and monitoring risk across the life cycle, including opportunities as well as threats, the risk and issue distinction, ownership, escalation, and the difference between qualitative and quantitative assessment.
Related
Learn in Curve is not affiliated with, endorsed by, or accredited by the Association for Project Management.