APM PMQ project life cycles: what you need to know

A life cycle is the set of phases a project moves through from start to handover. The PMQ tests whether you can choose between linear, iterative and hybrid for a given situation and justify the choice.

Updated

Life cycles look like the easiest topic on the syllabus and produce some of the weakest answers, because candidates learn the phase names and stop there. Naming the phases is worth very little. Saying which life cycle suits a described project, and why, is where the marks sit.

The phases, briefly

A linear life cycle moves through concept, where the idea is tested and an outline case is made, then definition, where the plan and the business case are developed in detail, then deployment, where the work is actually done, then transition, where the output is handed over and accepted.

That is the spine. What matters more is what each phase is deciding.

Project, extended and product life cycles

Three terms that look similar and are examined as a distinction.

The project life cycle ends at handover. The output exists and has been accepted.

The extended life cycle carries on past handover into benefits realisation, because an output that nobody uses has produced no benefit and the investment was justified on benefits.

The product life cycle is longer still. It covers the whole operational life of the thing, including its eventual decommissioning or disposal.

The reason this appears in scenarios: a sponsor asking whether the project succeeded is usually asking an extended life cycle question, and answering it with "we delivered on time" is answering the wrong one.

Linear, iterative, hybrid

Linear works through the phases in sequence, defining the output up front and then building it. It suits work where the requirements are stable and well understood, where the cost of change later is high, and where the output is physical.

Iterative repeats cycles of design, build and review, producing something usable early and refining it. It suits work where requirements are uncertain, where users cannot describe what they want until they see something, and where change is cheap.

Hybrid applies both to different parts of the same project.

However, the exam almost never gives you a clean case. It gives you a project with a fixed regulatory deadline and half-formed user requirements, and the marks are in the reasoning rather than the label.

Gate reviews

A gate review sits between phases and asks a decision, not a status question: does this project still justify continuing, and is it ready for the next phase?

Three outcomes are worth naming in an answer. Proceed. Proceed with conditions. Stop.

Stop is the one candidates omit and the one that makes governance real. A gate that can only say yes is a formality.

A worked example

Take a project replacing a customer-facing booking system in an organisation that also has to refit twelve physical service desks to match it.

A weak answer picks one life cycle for the whole thing.

A stronger answer splits it. The software is a good iterative candidate: the users cannot fully specify what they need in advance, early releases will produce better requirements than a workshop will, and changing software is comparatively cheap. The desk refit is a good linear candidate: the design has to be fixed before anything is manufactured, the work is physical, and changing it after installation is expensive and disruptive.

Then it names the consequence, which is where the better marks are. A hybrid needs a defined integration point, so the desk design has to be frozen at the moment the software's core interaction model is stable, and that freeze becomes a gate rather than an assumption.

Choosing, and defending the choice

You've got four questions that will carry most scenario answers on this topic. How well are the requirements understood now. How expensive is change later. How much does the customer need to see something before they can decide. And is there a fixed external date that constrains everything else.

Essentially: learn the phases once, then spend your revision time on the choice. The exam is testing whether you can look at a described project and say which life cycle fits it, what that decision costs you, and where the gates go.

Sim Samaar Shened, founder of Learn in Curve

Founder,Learn in Curve

Frequently asked questions

  • The phases of a linear life cycle, the differences between linear, iterative and hybrid approaches, how to select an approach for a given context, the purpose of gate reviews, and the distinction between project, extended and product life cycles.

Ready to check where you stand?

Fifteen questions in real APM PMQ format. No account required.